← All projectsCC04019
Project portal · built 17 Nov 2026, 10:03 am AEST · With client

Sanura Lura - 1871 GCH Frankie

BDCM

What's new

Monday updates and SharePoint changes, newest first

Full update log

Crompton Concepts prepares the traffic management for BDCM on this project. 1 Monday request is open; the most pressing is at the with client stage; the current CTMP on SharePoint is Rev 06; 6 TGS suites on file (General no rev, S1 Rev 06, S2 no rev, S5 Rev 02…). On the permit boards: 6 permits in force and 1 in progress. Monday holds 26 requests for this job (0 new, 26 amendments); all of them are on this page. Every file opens straight from SharePoint.

Client
BDCM
Crompton job
CC04019
Location
Sanura Lura - 1871 GCH Frankie
LGA / authority
—
Project coordinator
—
Latest planner · TMD
C.R · Christopher Wright
Monday project status
—
Deliverables
—
Permits (Monday)
6 in force · 1 in progress
Last activity
13 Nov 2026
Files on SharePoint
1,513 in 353 folders

What needs attention now

  1. Issued, waiting on client: CC04019-S7 - Rev 4 - BDCM - 1871 Gold Coast Highway. Required by 30 Sep 2026. Planner: C.R · TMD: Christopher Wright · Last note (15 Oct 2026, Permits): “Plans sent to client - Kerri 1410 Shaz Re_ BDCM - Lura - Revised TGS.eml”
  2. Permit in progress: KDR (Gold Coast) is KDR Pending. Follow up 24 Nov 2026. Wanted from 26 Jan 2027.
  3. Renewal date passed: RCP – Electrical PMT (TMR), renewal 17 Nov 2026, permit runs to 12 Dec 2026.
  4. Renewal date passed: TCP General Constructions (TMR), renewal 17 Nov 2026, permit runs to 16 Dec 2026.
  5. Renewal date passed: RCP – Access (TMR), renewal 17 Nov 2026, permit runs to 17 Dec 2026.
  6. Renewal date passed: RCP – Hardstand (TMR), renewal 17 Nov 2026, permit runs to 17 Dec 2026.
  7. Renewal date passed: RCP – Bollard & Screen System (TMR), renewal 17 Nov 2026, permit runs to 17 Dec 2026.

PPermits

9 permit lines on the Monday permit boards: 6 in force, 1 in progress. Newest first within each state; closed and expired permits are at the bottom.

PermitAuthorityTypeStatusPeriodSentFollow upRenewalPermit no.
KDR
Team Kerri · Gold Coast Permits - Kerri
Gold CoastOngoingIn progress
KDR Pending
26 Jan 2027 – 30 Jun 202710 Nov 202624 Nov 202619 May 2027
RCP – Electrical PMT
Team Kerri · TMR Permits - Kerri
TMRDate SpecificIn force
Done
1 Apr 2026 – 12 Dec 202616 Mar 202617 Nov 2026
TCP General Constructions
Team Kerri · TMR Permits - Kerri
Register: Ext 2 · App A-16306 · Permit TCP2026-56227-A2 · Invoiced · PC check: GTG permit folder
TMROngoingIn force
Done
1 Nov 2026 – 16 Dec 202630 Oct 202617 Nov 2026
RCP – Access
Team Kerri · TMR Permits - Kerri
TMROngoingIn force
Done
1 Apr 2026 – 17 Dec 202623 Mar 202617 Nov 2026
RCP – Hardstand
Team Kerri · TMR Permits - Kerri
TMROngoingIn force
Done
1 Apr 2026 – 17 Dec 202616 Mar 202617 Nov 2026
RCP – Bollard & Screen System
Team Kerri · TMR Permits - Kerri
TMROngoingIn force
Done
1 Apr 2026 – 17 Dec 202616 Mar 202617 Nov 2026
Footpath Continuous Occupation
Team Kerri · Gold Coast Permits - Kerri
FootpathOngoingIn force
Done
11 Nov 2026 – 19 Feb 202722 Oct 202614 Dec 2026
Footpath Operational
Team Kerri · Gold Coast Permits - Kerri
FootpathOngoingApproved, starts later
Done
19 Nov 2026 – 19 Feb 20279 Nov 20265 Jan 2027
S33
Team Kerri · TMR Permits - Kerri
TMROngoing
Done

01New to the project? Start here

  1. 1

    Understand the job

    Start with the current traffic management plan, then the client's project information.

  2. 2

    Open the current TGS set

    Latest revision of each suite. Earlier revisions are in the register and the file list.

  3. 3

    Know the paperwork

    Project information, contacts, permits, quotes and invoices, as filed on SharePoint.

  4. 4

    Catch up on correspondence

    The latest emails saved into the project folder.

02Document register

Latest revision of each TMP, TGS suite and report, read from the revision folders and file names on SharePoint. Archived and superseded folders are left out.

SuiteDocumentLatestSavedRevsCurrent files
—CTMPRev 0622 Jul 2024610.7 CC04019-CTMP-Sanura-Rev 6.pdfCC04019-CTMP-Sanura-Rev 6.pdf
—TMPRev 0430 Sep 20265CC04019-TMP-S7-Sanura-Rev 04.pdf
—RARev 0130 Sep 20262Risk Assessment-S7-Rev01.pdf
—TIAno rev2 Nov 20260TIA - Authority to Commence - s33_1.pdfTIA - Conditional Approval - s33 - Major Works_1.pdf
GeneralTGSno rev1 Aug 20240Appendix A - S3 - Stage 1- Combined TGS-compressed.pdf
GeneralWorkzone planno rev11 Aug 20250Workzone Drawings.pdf
S1TGSRev 0622 Jul 2024110.8 CC04019-S1-TGS-Rev 6.pdfCC04019-S1-TGS-Rev 6.pdf
S2TGSno rev11 Aug 20240CC04019-S2-TGS.pdf
S5TGSRev 0211 Aug 20251CC04019-S5-TGS-Rev 02 (1).pdf
S6TGSRev 005 Mar 20261CC04019-S6-TGS-Rev 00.pdf
S7TGSRev 032 Oct 20264CC04019-S7-TGS-Rev 03.pdf
S7Workzone planRev 0430 Sep 20265Appendix I - Workzone Drawings.pdf

03Requests on Monday

26 requests since 31 Jul 2024: 0 for new plans and 26 amendments to this job, newest first. Amendments stay on this page, never as a separate project.

RequestTypeSuiteRevStageRequestedRequired byPlannerTMD
CC04019-S7 - Rev 4 - BDCM - 1871 Gold Coast HighwayAmendmentS7Rev 04With client
Client review
28 Sep 202630 Sep 2026C.RChristopher Wright
CC04019-S7 - Rev 3 - BDCM - 1871 Gold Coast HighwayCouncil RFIS7Rev 03Invoiced
Invoiced
10 Sep 202612 Sep 2026
CC04019-S7 - Rev 2 - BDCM - 1871 Gold Coast HighwayAmendmentS7Rev 02Closed
No Charge
7 Sep 20269 Sep 2026
CC04019 - S7 - Rev 0 - BDCM - 1871 Gold Coast HighwayAmendmentS7Rev 00Invoiced
Invoiced
13 Apr 202615 Apr 2026
CC04019 - S6 - Rev 1 - BDCM - 1871 Gold Coast HighwayCouncil RFIS6Rev 01Closed
No Charge
5 Mar 20265 Mar 2026
CC04019 - S6 - Rev 0 - BDCM (1871 Burleigh Pty Ltd) - 1871 Gold Coast HighwayAmendmentS6Rev 00Closed
No Charge
19 Feb 202621 Feb 2026
CC04019 - S5 - Rev 5 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS5Rev 05Invoiced
Invoiced
26 Aug 202528 Aug 2025
CC04019 - S3 - Rev 14 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 14Closed
No Charge
25 Aug 202527 Aug 2025
CC04019 - S5 - Rev 4 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS5Rev 04Invoiced
Invoiced
15 Aug 202515 Aug 2025
CC04019 - S5 - Rev 3 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS5Rev 03Closed
No Charge
11 Aug 202513 Aug 2025
CC04019-S5 - Rev 2 - Frankie Construction - 1871 Gold Coast HighwayAmendmentS5Rev 02Closed
No Charge
5 Aug 20257 Aug 2025
CC04019 - S3 - Rev 13 - Frankie Construction - 1871 Gold Coast HighwayAmendmentS3Rev 13Invoiced
Invoiced
29 Jul 202531 Jul 2025
CC04019 - S3 - Rev 12 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 12Invoiced
Invoiced
27 Jun 202527 Jun 2025
CC04019 - S5 New Alignment - Frankie Construction - 1871 Gold Coast HighwayAmendmentS5Invoiced
Invoiced
18 Jun 2025
CC04019 - S3 - Rev 9 Client Amendments - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 09Invoiced
Invoiced
9 May 20259 May 2025
CC04019-S9 - Frankie Construction - 1871 Gold Coast HighwayAmendmentS9Invoiced
Invoiced
29 Apr 20251 May 2025
CC04019 - S3 - Rev 8 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 08Invoiced
Invoiced
1 Apr 20251 Apr 2025
CC04019 - S3 - Rev 7 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 07Invoiced
Invoiced
18 Mar 202520 Mar 2025
CC04019 - S3 - Rev 6 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 06Invoiced
Invoiced
11 Feb 202512 Feb 2025
CC04019-S3-R5 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Paid
Paid
7 Feb 20257 Feb 2025
CC04019-S3 - Rev 5 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 05Closed
No Charge
31 Jan 20251 Feb 2025
CC04019 - S3 - Rev 4 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 04Invoiced
Invoiced
15 Jan 202516 Jan 2025
CC04019-S3-Rev3 - Frankie Construction - 1871 Gold Coast HighwayCouncil RFIS3Rev 03Paid
Paid
10 Dec 202410 Dec 2024
CC04019-S3-Rev 2 - Frankie Constructions - Sanura - 1871 GC HwyCouncil RFIS3Rev 02Closed
No Charge
6 Dec 20246 Dec 2024
CC04019-S1-R9 - Frankie Construction - 1871 Gold Coast HighwayAmendmentS1Paid
Paid
4 Nov 202415 Nov 2024
CC04019 - Frankie Construction - 1871 Gold Coast HighwayAmendmentClosed
No Charge
31 Jul 202431 Jul 2024

04Who's who

From the Contact folders on SharePoint and the people assigned on Monday. Check the project information folder for the latest contact list.

Client / site

  • Archive - Frankie
  • !! Archive and Updates !!
  • Marc.thomson@frankieconstructions.com.auMarc.thomson@frankieconstructions.com.au
  • ACCTSInvoices@frankieconstructions.com.au
  • ACCTS - Tommy Cull0414 137 742
  • All Plans to go to Marc and Dan
  • Dtim.webber@frankieconstructions.com.au
  • SM - Dan Currie Mobile0404134207
  • SMdan.currie@frankieconstructions.com.au
  • Nathan Burden Director0404 000 315 · nburden@bdcm.com.au
  • Senior CA Matthew Higginsmhiggins@bdcm.com.au
  • Tom Cull - Does not need to be includedtommycull@gmail.com
  • twhite@bdcm.com.autwhite@bdcm.com.au

Crompton Concepts

  • C.RPlanner
  • Christopher WrightTMD

05Update log

Monday updates and replies on this project's requests, newest first.

  1. 15 Oct 2026, 9:24 am · Permits · CC04019-S7 - Rev 4 - BDCM - 1871 Gold Coast Highway

    Plans sent to client - Kerri 1410 Shaz Re_ BDCM - Lura - Revised TGS.eml

  2. Hi @K.R , Can you please advise if Chris will take over the TMD review on behalf of Aaron? There are multiple internal discussions with this project and we might need to discuss it with Chris first prior to the checking of plans. This is now for review. Accounts: 1xAdd'l TGS (S7-Rev03-12A/B) 6xTGS Amendment 1xTMP Amendment Link: S7 - Final Layout > Rev04

    • 2 Oct 2026, 8:38 am · Christopher Wright

      Hi @C.R If these is anything specific I should know just send me a message.

    • 2 Oct 2026, 9:10 am · Christopher Wright

      This is GTG

  3. 28 Sep 2026, 4:05 pm · Permits · CC04019-S7 - Rev 4 - BDCM - 1871 Gold Coast Highway

    Hi, Save Work Here: Plans CC04019 > S7 - Final Layout > Rev04 Folder Name: Sanura - 1871 GCH Frankie (Arlo) Instructions: The client would like the option designed with two controllers and the three controllers. Can we add the TGS's from the previous Revisions and have the new arrangement with the two controllers that you recently designed as a 2nd option when required. Site has advised that they will utilise the 2 TC arrangement when they are doing crane lifts and small ute deliveries. The 3TC arrangement will be implemented with Larger deliveries - bigger vehicles which restrict line of site. The site will determine which arrangement based on their daily needs on site. Thanks, Iris (280926)

  4. 23 Sep 2026, 10:54 am · Permits · CC04019-S7 - Rev 3 - BDCM - 1871 Gold Coast Highway

    IV0025358 sent to client - Shaz 2309 Invoice IV0025358 from Crompton Concepts for BDCM - 1871 Gold Coast Highway.eml 1x TMPA 1x 5TGA 1x AMENDPA

  5. Invoicing Notes - @Riri D. 1 x TMP Amendment 1 x Addition Plan - TC Hold Proceedure - Requested by TMD to reduce traffic control numbers. 1 x TGS Amendment to cover all 8 plans with updated arrangement.

  6. @K.R GTG. I have done some minor amendments. Give it 5 mins to update online.

  7. @C.R Kerri will give instructions

    • 14 Sep 2026, 8:06 am · C.R

      Got this, Aaron. Will just wait for Kerri's advice. Thank you.

    • 14 Sep 2026, 3:01 pm · K.R

      @C. Hi Cleo, At Aarons request, could you please create a TC Hold Procedure to be attached at the back of the TGS suite. Please have it designed like the occupation map. Written Instructions are saved in the Rev 3 Folder can you please add a diagram and jazz it up a bit for me . Thanks. Traffic Controller Pedestrian Proceedure is the doc.

    • 14 Sep 2026, 4:56 pm · C.R

      Hi @A.A and @K.R , This has been amended accordingly. Thank you! Link: Sharepoint - Rev03 - All Documents

  8. Hi @K.R , As mentioned on teams, most of the comments from Mark were already addressed in the previous versions of the plan. I only elaborated it in this revision by adding notes and an additional pedestrian signage. This is now for review. Anything else needed, please let me know. Thank you! Accounts: 8xTGS Amendment 1xTMP Amendment Link: Sharepoint - Rev03 - All Documents

    • 11 Sep 2026, 2:29 pm · C.R

      Hi @K.R , Amended per teams' instructions. This is now for final review. Thank you!

  9. No Charge - Per Mark When Completed

  10. No Charge - Per Mark

  11. 10 Sep 2026, 9:10 am · Permits · CC04019-S7 - Rev 3 - BDCM - 1871 Gold Coast Highway

    Hi @C.R Please save work here: S7 - Final Layout > Rev03 Plans folder: Plans CC04019 Kerri will add the details below. Thanks - Shaz

    • 10 Sep 2026, 9:22 am · K.R

      @C.R Coulld you please make the above amendments to the plans for Frankie. This is per a site visit yesterday by Mark. This can be prioritised over the TMP for Bay Terrace. - Many thanks

  12. @K.R GTG

  13. @C.R Can you change the first WM/40/RW to WM/40/RS? Thank you.

    • 8 Sep 2026, 10:38 am · C.R

      Hi @A.A , Thank you for this. TGS and TMP are now for final review. Link: Sharepoint - Rev02 - All Documents

  14. Hi @A.A /@K.R , This is now for review. Thanks! Accounts: 8xTGS Amendment 1xTMP Amendment Link: Rev02

    • 7 Sep 2026, 3:46 pm · C.R

      Note: An internal discussion occurred between me and Aaron earlier today. On top of the initial amendment request, we have agreed on the specific location of the 40km/hr speed reduction past Third Avenue so that we maintain the 200m minimum buffer zone.

  15. 7 Sep 2026, 9:47 am · Permits · CC04019-S7 - Rev 2 - BDCM - 1871 Gold Coast Highway

    Hi @C.R Plans folder: Plans CC04019 Suite: S7 - Final Layout Save work here: TGS/TMP > Rev02 Quote: none Request type: Amendment Scope: TGS & TMP Notes: Could you please update the Signage on TGS's as per the below instructions from Aaron. All 40 symbols in Insert A @ Third Avenue to be replace by yellow inserts as well as the End 40 in Third Ave. The first truck symbol between Second and First Ave to be replaced with 40 Reduce Speed. All TGS's to be updated to reflect change and TMP updated with new images. JHG finalising line marking for light rail project - 60km/h linemarked on roadway per image in Kieran's email. Please show this update also on TGS. Thank you. Please teams Kerri when completed so that permit folders can be updated and additional signage to be quoted. Installation of 60km_h Numerals on GCHwy SB - North of Third Ave.eml - Shaz

    • 7 Sep 2026, 11:41 am · C.R

      Update: I have reached out to Aaron and Kerri regarding specific confirmations. Waiting on their response before taking action as it will most likely affect the overall amendment request. Thanks.