← All projectsCC05146
Project portal · built 17 Nov 2026, 10:03 am AEST · TMD review We supply traffic control

ELEMENTS, BUDDS BEACH

McNab

What's new

Monday updates and SharePoint changes, newest first

Full update log

Crompton Concepts prepares the traffic management for McNab on this project at ELEMENTS BUDDS BEACH - BIRT AVE, Surfers Paradise, QLD. 1 Monday request is open; the most pressing is at the TMD review stage; the current CTMP on SharePoint is Rev 05; 5 TGS suites on file (General no rev, S1 no rev, S2 Rev 02, S3 Rev 04…). On the permit boards: 2 permits in force and 2 in progress. Monday holds 28 requests for this job (2 new, 26 amendments); all of them are on this page. Every file opens straight from SharePoint.

Client
McNab
Crompton job
CC05146
Location
ELEMENTS BUDDS BEACH - BIRT AVE, Surfers Paradise, QLD
LGA / authority
City of Gold Coast
Project coordinator
K.G
Latest planner · TMD
—
Monday project status
Amendment Review in Process
Deliverables
Engineering Design, TGS, Council Road Permit
Permits (Monday)
2 in force · 2 in progress
Last activity
16 Nov 2026
Files on SharePoint
1,116 in 320 folders

What needs attention now

  1. Needs TMD review: CC05146-S1 - Rev 20 - McNab - Budds Beach Elements. Required by 23 Oct 2026 (overdue). TMD: Christopher Wright · Last note (26 Oct 2026, KB.R): “Hi @Christopher Wright @K.R @K.G, As discussed, here are the TGS, TMP, and RA for this allocation under a new suite. The TGS was sent out last Friday as coordinated with Mark and…”
  2. Permit in progress: Monthly Concrete Pour Permit – OOH (Gold Coast) is Council Pending. Follow up 13 Nov 2026. Wanted from 12 Nov 2026.
  3. Permit in progress: Daily Operational Permit (Gold Coast) is Fee Quote/Notice to Pay Received / Sent. Follow up 13 Nov 2026. Wanted from 18 Nov 2026.

PPermits

5 permit lines on the Monday permit boards: 2 in force, 2 in progress. Newest first within each state; closed and expired permits are at the bottom.

PermitAuthorityTypeStatusPeriodSentFollow upRenewalPermit no.
Monthly Concrete Pour Permit – OOH
Team Kerri · Gold Coast Permits - Kerri
Gold CoastOngoingIn progress
Council Pending
12 Nov 2026 – 13 Dec 202628 Oct 202613 Nov 202616 Nov 2026
Daily Operational Permit
Team Kerri · Gold Coast Permits - Kerri
Gold CoastOngoingIn progress
Fee Quote/Notice to Pay Received / Sent
18 Nov 2026 – 21 Feb 202711 Oct 202613 Nov 20267 Jan 2027
De watering
Team Kerri · Gold Coast Permits - Kerri
Gold CoastOngoingIn force
Done
12 Mar 2026 – 12 Mar 202726 Feb 202629 Jan 2027
KDR – Light Rail Approval
Team Kerri · Gold Coast Permits - Kerri
Gold CoastOngoingIn force
Done
16 Nov 2026 – 31 May 20274 Nov 202615 Apr 2027
Gantry Occupation
Team Kerri · Gold Coast Permits - Kerri
Gold CoastOngoingApproved, starts later
Done
17 Dec 2026 – 31 May 202716 Nov 20261 Dec 20261 Feb 2027

01New to the project? Start here

  1. 1

    Understand the job

    Start with the current traffic management plan, then the client's project information.

  2. 2

    Open the current TGS set

    Latest revision of each suite. Earlier revisions are in the register and the file list.

  3. 3

    Know the paperwork

    Project information, contacts, permits, quotes and invoices, as filed on SharePoint.

  4. 4

    Catch up on correspondence

    The latest emails saved into the project folder.

02Document register

Latest revision of each TMP, TGS suite and report, read from the revision folders and file names on SharePoint. Archived and superseded folders are left out.

03Requests on Monday

28 requests since 20 Aug 2024: 2 for new plans and 26 amendments to this job, newest first. Amendments stay on this page, never as a separate project.

RequestTypeSuiteRevStageRequestedRequired byPlannerTMD
CC05146-S1 - Rev 21 - McNab - Budds Beach ElementsAmendmentS1Rev 21Closed
No Charge
28 Oct 202630 Oct 2026
CC05146-S1 - Rev 20 - McNab - Budds Beach ElementsAmendmentS1Rev 20TMD review
Requested Info
21 Oct 202623 Oct 2026KB.RChristopher Wright
CC05146-S1 - Rev 19 - McNab - Budds Beach ElementsAmendmentS1Rev 19Closed
No Charge
28 Sep 202630 Sep 2026
CC05146-S3 - Rev 2 - McNab - Elements Budds BeachAmendmentS3Rev 02Closed
No Charge
22 Sep 202624 Sep 2026
CC05146-S1 - Rev 18 - McNab - Budds Beach ElementsAmendmentS1Rev 18Closed
No Charge
25 Aug 202627 Aug 2026
CC05146-S1 - Rev 17 - McNab - Budds Beach ElementsAmendmentS1Rev 17Closed
No Charge
4 Aug 20266 Aug 2026
CC05146-S3 - Rev 1 - McNab - Budds Beach ElementsAmendmentS3Rev 01Closed
No Charge
3 Aug 20267 Aug 2026
CC05146 - S3 - McNab - Elements Budds BeachNew plansS3Closed
No Charge
20 Jul 202624 Jul 2026
CC05146 - S2 - Rev 4 - McNab - Elements Budds BeachCouncil RFIS2Rev 04Invoiced
Invoiced
9 Feb 202611 Feb 2026
CC05146-S2 - LTR - McNab - Elements Budds BeachAmendmentS2Closed
No Charge
17 Sep 202519 Sep 2025
CC05146-S2 - TMP Rev 4 - McNab - Elements Budds BeachCouncil RFIS2Rev 04Closed
No Charge
4 Sep 20255 Sep 2025
CC05146-S2 - Rev 02 TMP Rev 03 - McNab - Elements Budds BeachCouncil RFIS2Rev 02Closed
No Charge
1 Sep 20253 Sep 2025
CC05146-S2 - Rev 01 TMP Rev 2 - McNab - Elements Budds BeachAmendmentS2Rev 01Invoiced
Invoiced
22 Aug 202524 Aug 2025
CC05146-S1 - Rev 19 - McNab - Elements Budds BeachAmendmentS1Rev 19Closed
No Charge
7 Aug 20259 Aug 2025
CC05146-S1 - Rev 15 - McNab - Elements Budds BeachAmendmentS1Rev 15Invoiced
Invoiced
28 Jul 202530 Jul 2025
CC05146- S2 Rev 1 - McNab - Elements Budds BeachAmendmentS2Rev 01Closed
No Charge
16 Jul 202516 Jul 2025
CC05146-S2 - McNab - Elements Budds BeachAmendmentS2Invoiced
Invoiced
6 Jun 202519 Jun 2025
CC05146-S1 - Rev 16 - McNab - Elements Budds BeachAmendmentS1Rev 16Invoiced
Invoiced
30 May 20251 Jun 2025
CC05146-S1 - Rev 15 - McNab - Elements Budds BeachAmendmentS1Rev 15Invoiced
Invoiced
21 May 202524 May 2025
CC05146 - McNab - Elements Budds BeachCouncil RFIClosed
No Charge
3 Mar 20253 Mar 2025
CC05146- Rev 13 - McNab - Elements Budds BeachCouncil RFIRev 13Closed
No Charge
20 Feb 202520 Feb 2025
CC05146 - McNab - Elements Budds BeachCouncil RFIClosed
No Charge
18 Feb 202520 Feb 2025
CC05146 - McNab - Elements Budds Beach - Signage change - Rev7Council RFIRev 07Closed
No Charge
3 Feb 20255 Feb 2025
CC05146 - McNab - Elements Budds Beach - Additional Stormwater TGSAmendmentPaid
Paid
15 Jan 202517 Jan 2025
CC05146 - McNab - Budds Beach - 21 Oak Ave SurfersAmendmentClosed
No Charge
7 Jan 20259 Jan 2025
CC05146 - McNab - Budds BeachAmendmentInvoiced
Invoiced
17 Dec 202418 Dec 2024
CC05146 - McNab - Elements Budds BeachAmendmentClosed
No Charge
5 Sep 20245 Sep 2024
CC05146 - McNab - Elements Budds BeachNew plansClosed
Paid
20 Aug 2024

04Who's who

From the Contact folders on SharePoint and the people assigned on Monday. Check the project information folder for the latest contact list.

Client / site

  • !!!! All permits to go to Grant
  • !!!! PLEASE MAKE SURE ALL TRAFFIC INVOICES ARE COPIED INTO WILLIAM HARLOW
  • All letterbox dropswill.richardson@mcnab.net.au
  • Archive
  • Aaron.Groot@mcnab.net.auAaron.Groot@mcnab.net.au
  • Ben.Johnson@mcnab.net.auBen.Johnson@mcnab.net.au
  • CA- John Sunjohn.sun@mcnab.net
  • HSE Grant Allen
  • HSEGrant.allen@mcnab.net.au
  • Kurt LarsenKurt.Larsen@mcnab.net.au
  • PLEASE MAKE SURE ALL TRAFFIC INVOICES ARE COPIED INTO WILLIAM HARLOW
  • PM Simon Rua0418 655 184
  • SM Mitchell Cameron0418879618
  • SMMitchell.cameron@mcnab.net.au
  • Will Richardson - - all letterbox dropswill.richardson@mcnab.net.au

Crompton Concepts

  • KB.RPlanner
  • Christopher WrightTMD
  • K.GProject coordinator (Monday)

05Update log

Monday updates and replies on this project's requests, newest first.

  1. No Charge per Mark

  2. No Charge per Mark

  3. Hi @Christopher Wright @K.R, For CC05146-S1 - Rev 21 - McNab - Budds Beach Elements, I've tried to have this submitted for review using Sanju's app but given the urgency of this allocation, I wasn't able to fully edit everything out that was noted as "Tidy Up". Some of the edits that are required here would be editing the TMP template in general. Considering that this is an old template that we used, it would naturally be not up to date. Also, given that this was previously accepted by Council, everything written before here was previously accepted. Doing an overhaul of the changes in the TMP would require much more effort to do and would not be feasible under my time as I have an allocation from HEH Civil that I would be prioritising after this. S1: 13xTGS Amendment 1xTMP Amendment 1xRA Amendment S3: 1xTGS Add'l 16xTGS Amendment 1xTMP Amendment 1xRA Amendment Links: S1 - TGS -R21 S1 - TMP - R24 S3 - TGS - Rev 4 S3 - TMP - Rev 2 It is now available for review.

    • 2 Nov 2026, 11:55 am · Christopher Wright

      This is GTG

  4. 28 Oct 2026, 3:29 pm · Permits · CC05146-S1 - Rev 21 - McNab - Budds Beach Elements

    Hey Kerby, I really need S4 to be a new revision of S1 as that is the currently approved version and we must show all changes. I will then need S3 to reflect the signage changes we made. I know this is confusing but I need to get this right. S1 - TGS -R21 S1 - TMP - R24 S3 - TGS - Rev 4 S3 - TMP - Rev 2 Plans Folder: Plans - CC05146 Project Folder: ELEMENTS, BUDDS BEACH

  5. Hi @Christopher Wright @K.R @K.G, As discussed, here are the TGS, TMP, and RA for this allocation under a new suite. The TGS was sent out last Friday as coordinated with Mark and Kelly. I had then used the template from S3 TMP and adjusted everything to match S4 TGS details. I've made it more comprehensive from how it was before and had removed parts that are not applicable to the current set of TGS. The desktop risk assessment and the one in the TGS has also been updated. The AV and concrete truck swept path and road occupancy has been kept as is. Accounts: NEW SUITE (S4) 5xTGS 1xTMP 1xRA Link: TGS: S4 > Rev0 TMP: S4 > Rev0 It is now available for review. Thanks!

  6. Hi @Christopher Wright @K.R, Following format of existing TGS, layout was kept as is for the additional TGS to maintain consistency. Same goes to sign formats here. I've combined approved TTM setups into one to convey half road closure with detour and SLRF along Oak Avenue and Birt Avenue. I've made changes both RA in the TGS and TMP to make everything consistent. Summary of changes are all noted in the change logs. Accounts: 1xTGS Add'l (TGS 17) 5xTGS Amendment (TGS 3, 4, 6, 14, & 17 risk assessments only) 1xTMP Amendment 1xRA Amendment Links: TGS: S1 > R20 TMP: S1 > R23 It is now available for review. Thank you!

  7. 21 Oct 2026, 3:30 pm · Permits · CC05146-S1 - Rev 20 - McNab - Budds Beach Elements

    Hi @KB.R Please save work here: TGS: S1 > R20 TMP: S1 > R23 Kerri will add details below. Thank you - Shaz

  8. Hi @Christopher Wright @K.R, I've uploaded the amended S3 files following the document provided by the client and as per Teams meeting with Chris. This is already S3 Rev03. Just reusing this Monday line for it. Also, I've used an updated RA template for this one which is a bit more comprehensive and this was the updated RA I used for S1 Rev19 for this client as well. Summary of changes are noted in the change logs for both TGS and TMP. It is now available for review. Accounts: 1xAdditional TGS 9xTGS Amendment 1xTMP Amendment 1xRA Amendment Link: TGS: Rev 03 TMP: Rev01 It is now available for review. Thank you!

    • 14 Oct 2026, 12:49 pm · Christopher Wright

      It appears that all amendments have been made, this is GTG

  9. Hi @K.R @Christopher Wright, I've amended the TGS reflecting usage of portabooms where applicable. Particularly TGS 3, 7, and 14 where TC locations could be replaced with Portabooms. I was only able to reflect both portabooms for TGS 1 like TGS 4 as this is the only other setup that do not require holding of traffic along Birt Avenue and the other side of Oak Avenue. I've added in a note in TGS 12 where TC shall advise workers to cross when all traffic is held. Accounts: 5xTGS Amendment 1xTMP Amendment Link: TGS Rev19: R19 TMP Rev22: R22 It is now available for review. Thank you!

    • 2 Oct 2026, 11:08 am · Christopher Wright

      This is GTG

  10. 1 Oct 2026, 2:33 pm · Riri D. · CC05146-S3 - Rev 2 - McNab - Elements Budds Beach

  11. No Charge - Updated to Rev 19

  12. No Charge - Client has purchased porta booms.

  13. Hi @K.R @Christopher Wright, As discussed, I've amended TGS 12 and noted it as their alternative daily arrangement. I've added in notes that TTM is managed either TC or portabooms and corresponding MMS signs shall be changed. However, following that TMP Rev21 was not considered. Hence, I've created first TMP Rev21 that was supposedly added for TGS Rev18. and then I used this TMP for Rev22 with TGS Rev19. I do like to note that in anyone of the folders, there is no RA attached and CTMP is not provided in previous versions. I've just followed this and had just uploaded a TMP version, rather than the CTMP one. Accounts: 1xTGS Amendment 2xTMP Amendment (Rev21 & Rev22) Link: TGS Rev19: R19 TMP Rev22: R22 TMP Rev21: R21 It is now available for review. Thank you!

    • 30 Sep 2026, 8:08 am · Christopher Wright

      Morning @KB.R Can you put together a risk assessment and add that please.

    • 30 Sep 2026, 9:06 am · KB.R

      Sure thing. I'll be using the old template for the RA, as there maybe previous risk RAs attached to older versions.

    • 30 Sep 2026, 9:47 am · Christopher Wright

      @KB.R Thank you

    • 30 Sep 2026, 11:15 am · KB.R

      Hi @Christopher Wright, I've uploaded the new Risk Assessment for S1 Plans. It is uploaded here: R22. I've uploaded a CTMP as well containing both TGS and Desktop RA. It is now for your review. Thank you! Accounts: 1xRA

    • 30 Sep 2026, 11:39 am · Christopher Wright

      @KB.R Thank you much appreciated.

    • 30 Sep 2026, 11:39 am · Christopher Wright

      This is GTG

    • 1 Oct 2026, 12:13 pm · K.R

      @KB.R Hi Kerby,, The booms on Oak are in the wrong place on a few of the TGS's , could you please amend to have one at either end of site on Oak per the below. This is where they will be placed on all arrangement that have the half road on Oak then there is the two on Birt. Can you please amend where necessary and update the images in the TMP.

    • 1 Oct 2026, 12:29 pm · KB.R

      Hi @K.R. I can amend TGS 1 and 3 and include 2 portabooms at that location as these setups are half-road closures. Though, the one in your screenshot is configured as a single lane reversible flow. Queued traffic will block the open lane and the intersection if we are having the portabooms at that area. I've encircled the areas where portabooms are placed, in which per previous instruction, an option will be provided to either use TC or portabooom.

    • 1 Oct 2026, 12:56 pm · KB.R

      @K.R to confirm with client about setup.

  14. 28 Sep 2026, 9:48 am · Permits · CC05146-S1 - Rev 19 - McNab - Budds Beach Elements

    Hi Team! Please save work here: TGS R19 TMP R22 Plans folder: Plans - CC05146 update the daily arrangement plans - Half road with detour on Oak Ave with either parking lane or half road with hold and release or hold and release on Birt ave. We need to show the option of either portaboom or TC's on these plans. Please update TMP with updated images. Update revision and change log. This is urgent. Thanks - Shaz

    • 28 Sep 2026, 10:28 am · KB.R

      Hi @Permits, could you please include the folder of the main plans as well. I can't access previous revisions of the TGS and the TMP with just the links you have provided. Thank you.

    • 28 Sep 2026, 10:43 am · KB.R

      Hi @K.R, With the main plans not being included, I've backtracked CC05146-S1 - Rev 18 - McNab - Budds Beach Elements. I noticed that for Rev21 folder, there are no TMP files uploaded. there's only a word file there advising a new S3 TMP will be created which is a direct copy of S1. Am I amending S3 TMP Rev00 for this or will I be using S1 TMP Rev20?

    • 28 Sep 2026, 10:56 am · Permits

      @KB.R added above and dropping here: Plans - CC05146 Apologies, missed to add it. thank you.

    • 28 Sep 2026, 10:58 am · Permits

      @K.R please assist Kerby for the above query.. thank you.

  15. 22 Sep 2026, 9:20 am · Permits · CC05146-S3 - Rev 2 - McNab - Elements Budds Beach

    Hi, Plans folder: Plans - CC05146 Suite: S3 Save work here: TGS > S3 -Pending Lono > Rev 2 TMP >S3 - Pending LONO Project location: ELEMENTS, BUDDS BEACH McNab Budds Beach TGS Folder Location S3 -Pending Lono TMP Folder Location S3 - Pending LONO Please ensure that S3 TMP is based on S1 Signage - I think that this has been done previously. We need to show signage options of TC and Portaboom options. Can you please also add a section in the TMP for After Hours Permit Requirements:- * Monthly out of hours permit - Precast/Oversize Deliveries and Concrete Pours - Work is to be carried out between the hours of 5:00am and 6:30pm, a maximum of two days per week, Monday – Friday - Agreed with Peter Lowery. Project is up to Level 7 - anything prior can be marked as completed. Key considerations; * Keep existing permanent signage setups and no daily utes * Reduce Traffic Controllers * Footpath closures required for external works later - Please add this section also * Added high impact activities date specific for road reinstatement/ asphalting as required by council officers, extent can’t be quantified until final inspection - Please add a section of this to be advised closer to the end of the project. Client Comments on PDF for Full Closure Arrangements:- Requesting this set up for concrete pours moving forward . Could you please replace the figure 17 - Section 8.8 Site Setup with below Copy of client email chain saved in folder - please add schedule - this is subject to weather -…

    • 22 Sep 2026, 5:26 pm · B.R

      Hi @K.R, Kindly let me know once there’s any information & markup regarding the full road closure. May I also ask where the pdf is located? Thank you!

    • 23 Sep 2026, 10:39 am · Riri D.

      @B.R it is saved under Rev 2

    • 23 Sep 2026, 2:30 pm · B.R

      Thanks @Riri D., just waiting for the Road closure info to include in the S3 revision thank you!

    • 23 Sep 2026, 3:46 pm · K.R

      @B.R the client has made comments on the TGS's

    • 24 Sep 2026, 5:46 pm · B.R

      Hi @Christopher Wright, This is uploaded and for review. kindly let me know if any changes are needed. Thank you very much! These are the changes made as discussed in the Teams chat with @K.R , in conjunction with the above revisions: Teams reference: Requested based on Updates.doc (in folder) 1. Updated the TMP to reflect that only S3 is currently being undertaken, with no changes at this stage to any other suites. 2. Reduce Traffic Controllers - Revision from Updates.doc (photo below) - Amended TGS 7B, 12B & 15B 3. Added a section for Footpath Closures for External Works – Footpath Rectification Included a note that the full extent of the footpath closure requirement cannot be confirmed at this stage and will be confirmed upon final inspection. a footpath closure will be required, while the associated road impact will be confirmed at a later date - Added on CTMP-Section. 8.5.3 4. full…

    • 25 Sep 2026, 9:13 am · K.R

      Hi @B.R could you please amend this section to include 7B - Full Road Closure on Oak Ave and single lane on Birt Ave will be utilised for kerb and Chanel and Road reinstagement works - The extent of closure will be determined upon council inspection. A 24/7 closure will be required to complete these works. Footpath reinstatement will require full footpath closures on both frontages and with a lane on each frontage to complete these works - Please check that we have a TGS that shows these arrangements. I think we would need to do it one frontage at a time.

    • 25 Sep 2026, 10:35 am · B.R

      Hi @K.R This has been amended on TGS 7B - Section 8.4.5 Raft Pours. For the footpath reinstatement works, should I add an 1xadditional TGS or one TGS per frontage to show these works, as there is currently no TGS for this arrangement? Thanks!

    • 25 Sep 2026, 11:28 am · K.R

      @B.R yes please do the additional requirements for footpath reinstatements. Thanks

    • 25 Sep 2026, 2:54 pm · B.R

      Hi @Christopher Wright , I’ve re-uploaded the plans for your review, including the additional comments and updates. Thank you!

    • 28 Sep 2026, 11:46 am · Christopher Wright

      These appear to be GTG @K.R

    • 7 Oct 2026, 1:45 pm · K.R

      @KB.R could you please call @Christopher Wright to go through updates that are required from TMD Review. Thanks

    • 7 Oct 2026, 1:47 pm · K.R

      @KB.R we also need to ensure that the Portaboom updates you did on S1 are carried over to S3. Thanks

    • 9 Oct 2026, 11:25 am · KB.R

      Pending confirmations with Chris regarding revision document provided by client. To discuss through Teams. Revision document are S2 documents, but client had inserted three TGS from S1 Rev16 and S1 Rev10 that needs confirmation. Will work on the TMP while waiting.

06Every file and folder

1,116 files in 320 folders. Type part of a name, a suite, a revision or a street to narrow the list. Sort by name or by date saved.

TypeNameFolderSaved