← All projectsCC05840
Project portal · built 17 Nov 2026, 10:03 am AEST · Review amendments We supply traffic control

South Beach Project - Surfers Paradise

AConstruct

What's new

Monday updates and SharePoint changes, newest first

Full update log

Crompton Concepts prepares the traffic management for AConstruct on this project at Markwell Avenue, Surfers Paradise, QLD. 3 Monday requests are open; the most pressing is at the review amendments stage; the current CTMP on SharePoint is Rev 14; 6 TGS suites on file (S2 Rev 03, S3 Rev 06, S4 Rev 05, S5 Rev 02…). On the permit boards: 2 permits in force and 6 in progress. Monday holds 19 requests for this job (2 new, 17 amendments); all of them are on this page. Every file opens straight from SharePoint.

Client
AConstruct
Crompton job
CC05840
Location
Markwell Avenue, Surfers Paradise, QLD
LGA / authority
—
Project coordinator
C.H
Latest planner · TMD
Sean B · Christopher Wright
Monday project status
New
Deliverables
Council Road Permit, Footpath Permit, Police Permit, RA, TGS, TMP, TA
Permits (Monday)
2 in force · 6 in progress
Last activity
16 Nov 2026
Files on SharePoint
753 in 198 folders

What needs attention now

  1. Urgent Review comments to action: CC05840-S6 - Rev 2 - A Construct - South Beach - Surfers Paradise Blvd, Surfers Paradise. Required by 11 Nov 2026 (overdue). Planner: Sean B · TMD: Christopher Wright · Last note (16 Nov 2026, S.B): “Hi Sean and Neil, Thanks for working through the last round so quickly. I've checked CC05840-TGS-S6-Rev02.pdf in the Rev 02 folder against each point. These ones are confirmed in…”
  2. Urgent TMD approved, ready to issue: CC05840-S5 - Rev 2 - A Construct - South Beach - Surfers Paradise Blvd, Surfers Paradise. Required by 30 Sep 2026 (overdue). Planner: B.R · TMD: Christopher Wright · Last note (28 Sep 2026, Permits): “Hi Team! Please save work here: S5 - Daily Arrangement > Rev 02 Plans folder: Plans CC05840 Request: Please harmonize CC05840-S5-1C and CC05840-S5-6B as one plan and make it…”
  3. Issued, waiting on client: CC05840-S5 - Rev 1 - A Construct - South Beach - Surfers Paradise Blvd, Surfers Paradise. Required by 20 Aug 2026. Planner: J.G · TMD: Christopher Wright
  4. Permit in progress: A Construct (Installation - OOH) (Gold Coast) is Initial Pending. Follow up 20 Nov 2026. Wanted from 23 Nov 2026.
  5. Permit in progress: A Construct – South Beach (Enderley Ave) – Operational (Gold Coast) is Received/Holding. Follow up 19 Nov 2026. Wanted from 28 Nov 2026.
  6. Permit in progress: A Construct – South Beach (Enderley Ave) – High Impact (Gold Coast) is Fee Quote/Notice to Pay Received / Sent. Follow up 19 Nov 2026. Wanted from 28 Nov 2026.
  7. Permit in progress: A Construct (Installation - 24 Hours) (Gold Coast) is Initial Pending. Follow up 20 Nov 2026. Wanted from 23 Nov 2026.
  8. Permit in progress: A Construct (Installation - Daytime) (Gold Coast) is Initial Pending. Follow up 20 Nov 2026. Wanted from 23 Nov 2026.
  9. Permit in progress: A Construct – South Beach (Enderley Ave) – KDR Signage (Gold Coast) is Council Pending. Follow up 19 Nov 2026. Wanted from 1 Jan 2027.

PPermits

8 permit lines on the Monday permit boards: 2 in force, 6 in progress. Newest first within each state; closed and expired permits are at the bottom.

PermitAuthorityTypeStatusPeriodSentFollow upRenewalPermit no.
A Construct (Installation - OOH)
Team Neil · Gold Coast Permits - Neil
Gold CoastDate SpecificIn progress
Initial Pending
23 Nov 2026 – 23 Dec 20266 Nov 202620 Nov 202620 Nov 2026
A Construct – South Beach (Enderley Ave) – Operational
Team Neil · Gold Coast Permits - Neil
Gold CoastOngoingIn progress
Received/Holding
28 Nov 2026 – 28 Feb 202728 Oct 202619 Nov 202615 Dec 2026
A Construct – South Beach (Enderley Ave) – High Impact
Team Neil · Gold Coast Permits - Neil
Gold CoastOngoingIn progress
Fee Quote/Notice to Pay Received / Sent
28 Nov 2026 – 28 Feb 202727 Oct 202619 Nov 202615 Dec 2026
A Construct (Installation - 24 Hours)
Team Neil · Gold Coast Permits - Neil
Gold CoastDate SpecificIn progress
Initial Pending
23 Nov 2026 – 28 Feb 20276 Nov 202620 Nov 202615 Jan 2027
A Construct (Installation - Daytime)
Team Neil · Gold Coast Permits - Neil
Gold CoastDate SpecificIn progress
Initial Pending
23 Nov 2026 – 28 Feb 20276 Nov 202620 Nov 202615 Jan 2027
A Construct – South Beach (Enderley Ave) – KDR Signage
Team Neil · Gold Coast Permits - Neil
Gold CoastOngoingIn progress
Council Pending
1 Jan 2027 – 30 Jun 202729 Oct 202619 Nov 202624 May 2027
A Construct – Stormwater Works
Team Neil · Gold Coast Permits - Neil
Gold CoastDate SpecificIn force
Done
4 Nov 2026 – 24 Nov 202626 Oct 2026
A Construct – South Beach (Enderley Ave) – Stormwater Works
Team Neil · Gold Coast Permits - Neil
Gold CoastDate SpecificIn force
Done
11 Nov 2026 – 3 Dec 202626 Oct 2026

01New to the project? Start here

  1. 1

    Understand the job

    Start with the current traffic management plan, then the client's project information.

  2. 2

    Open the current TGS set

    Latest revision of each suite. Earlier revisions are in the register and the file list.

  3. 3

    Know the paperwork

    Project information, contacts, permits, quotes and invoices, as filed on SharePoint.

  4. 4

    Catch up on correspondence

    The latest emails saved into the project folder.

02Document register

Latest revision of each TMP, TGS suite and report, read from the revision folders and file names on SharePoint. Archived and superseded folders are left out.

03Requests on Monday

19 requests since 21 Oct 2025: 2 for new plans and 17 amendments to this job, newest first. Amendments stay on this page, never as a separate project.

RequestTypeSuiteRevStageRequestedRequired byPlannerTMD
CC05840-S6 - Rev 2 - A Construct - South Beach - Surfers Paradise Blvd, Surfers Paradise UrgentAmendmentS6Rev 02Review amendments
Internal Amendments
9 Nov 202611 Nov 2026Sean BChristopher Wright
CC05840-S5 - Rev 2 - A Construct - South Beach - Surfers Paradise Blvd, Surfers Paradise UrgentAmendmentS5Rev 02TMD approved
TMD Approved
28 Sep 202630 Sep 2026B.RChristopher Wright
CC05840-S5 - Rev 1 - A Construct - South Beach - Surfers Paradise Blvd, Surfers ParadiseAmendmentS5Rev 01With client
Client review
18 Aug 202620 Aug 2026J.GChristopher Wright
CC05840 - A Construct - South Beach - TGS AmendmentsAmendmentClosed
No Charge
24 Jul 202626 Jul 2026
CC05840 - A Construct - South Beach - Additional daily arrangement TGSsAmendmentClosed
No Charge
1 Jul 20263 Jul 2026
CC05840-S4 - A Construct - South Beach - Markwell Ave - LTS update onlyNew plansS4Closed
No Charge
5 Jun 20267 Jun 2026
CC05840-S4 - AConstruct - South Beach Project - RFI LONO Main WorksCouncil RFIS4Invoiced
Invoiced
12 Mar 202614 Mar 2026
CC05840-S4 - A Construct - South Beach - Client Amendments 27.02.26AmendmentS4Closed
No Charge
27 Feb 20261 Mar 2026
CC05840-S3 - A Construct - South Beach - Council amendmentsCouncil RFIS3Paid
Paid
10 Feb 202612 Feb 2026
CC05840-S3 - A Construct - South BeachCouncil RFIS3Closed
No Charge
4 Feb 20266 Feb 2026
CC05840-S3 - A Construct - South Beach - Works Zone PlanAmendmentS3Closed
No Charge
2 Feb 20264 Feb 2026
CC05840-S3 - A Construct - South BeachCouncil RFIS3Closed
No Charge
29 Jan 202631 Jan 2026
CC05840-S2 - A Construct - South Beach - Surfers Paradise Blvd, Surfers ParadiseAmendmentS2Closed
No Charge
20 Jan 202622 Jan 2026
CC05840-S2 - Rev 3 - A Construct - South BeachAmendmentS2Rev 03Closed
No Charge
7 Jan 20269 Jan 2026
CC05840 - S2 - R4 - A Construct - South Beach - Surfers Paradise Blvd, Surfers ParadiseAmendmentS2Closed
No Charge
19 Dec 202521 Dec 2025
CC05840-S2 - AConstruct - Cascade Gold CoastAmendmentS2Paid
Paid
28 Nov 20252 Dec 2025
CC05840-S2 - AConstruct - Cascade Gold CoastAmendmentS2Paid
Paid
11 Nov 202513 Nov 2025
CC05840-S2 - A Construct - Cascade Gold CoastNew plansS2Paid
Paid
5 Nov 20256 Nov 2025
CC05840-S1 - AConstruct - Cascade Gold Coast - Early works - hold and releaseAmendmentS1Paid
Paid
21 Oct 202523 Oct 2025

04Who's who

From the Contact folders on SharePoint and the people assigned on Monday. Check the project information folder for the latest contact list.

Crompton Concepts

  • NeilProject coordinator (folder flag)
  • Sean BPlanner
  • Christopher WrightTMD
  • B.RPlanner
  • J.GPlanner
  • C.HProject coordinator (Monday)

Client / site

  • 0. Archive and Updates!!
  • Adam Beard0417 737 097
  • CA - Clay Hartclay@aconstruct.com.au
  • Clay Hart0404 892 529
  • PM - Adam Beardadam@aconstruct.com.au
  • 1. Invoices toaccounts@aconstruct.com.au
  • CA - Gabriel Steinergabriel@aconstruct.com.au
  • CAgabriel@aconstruct.com.au
  • PM - Mario Crismani0411 745 228
  • PMmario@aconstruct.com.au
  • SSMhilton@aconstruct.com.au
  • Senior CA - Alan Lengsfeld0439 432 017
  • Senior Site Mgr - Hilton Wells
  • WHSE - Chris Muttonchris@aconstruct.com.au

05Update log

Monday updates and replies on this project's requests, newest first.

  1. Hi Sean and Neil, Thanks for working through the last round so quickly. I've checked CC05840-TGS-S6-Rev02.pdf in the Rev 02 folder against each point. These ones are confirmed in the PDF: the 7B truck note, the S5 references (S5-1C on 1B/2B/5B/10B, S5-6B on 7B/8B), the 30-second single-lane hold note, 2A and 10A updated, and the "DUPLICATE" and "Night works" labels removed. Several items marked "Actioned" aren't showing in the PDF yet, though, so I suspect the final export wasn't saved over the file: 1. Options analysis A sheets (not updated in the PDF) * 1A, 3A, 4A, 5A, 6A, 7A, 8A and 9A still say "This operation will require traffic controllers to hold the traffic which will conflict with the operating signals." 1B, 5B, 7B and 8B all use H&R with the TC waiting for the signals to go red, so at least 1A, 5A, 7A and 8A need H&R selected and that reasoning replaced. For the site-inactive and non-H&R sheets (3A, 4A, 6A, 9A) the wording can stay if H&R is genuinely not used there. 2. Speed (header vs ERW plates) * Your note says the ERW signs were correct and the header was updated instead, but every sheet header still reads "Road Speed: 40 km/hr", and the END ROADWORK / DRIVE SAFELY plates are still six x 50 and one x 40 on each B sheet. If SP Blvd is 50 and Markwell/Enderley are 40, please put both in the header (e.g. "Road Speed: 40 km/hr (Markwell/Enderley), 50 km/hr (Surfers Paradise Blvd)"). Then check that the single 40 plate is on the Markwell/Enderley exit and the 50s…

  2. Feedback from Sanju have been addressed as follows: Against the request: * 1B: other frontage, truck reversing note (30 sec hold) and H&R are all shown. Good. * 7B: H&R and the second frontage are shown, but there's no note on the truck movements like on 1B, 2B and 5B. Truck route is only in the legend. Please add the same truck entry/exit note so it reads the same as the others. -Actioned, shown notes * S5 Daily Arrangement: Riri flagged S5. I can't see S5 referenced anywhere on the sheets. If the other frontage is running under the S5 daily TGS, add a "refer to CC05840-S5-xx" note so the TCs know which plan covers it. -Actioned, shown reference TGS Needs fixing: * Options analysis sheets. The A sheets (2A, 5A and others) still say H&R isn't selected because holding traffic will conflict with the signals, but the B sheets now have the TC holding traffic and waiting for the signals to go red. Update the A sheets to match, and add a note on TC positioning relative to the signals. -Actioned, updated options analysis * Speed. Header says 40km/h but most of the ERW signs have 50 plates, with one 40. Confirm the posted limit on each approach (SP Blvd vs Markwell/Enderley) and make the ERW plates match. -Actioned, ERW signs correct, updated header instead * 2B has a "Night works" label on the water meter removal. Is that meant to be there? If not, take it out. -Actioned, removed label * 1B has a stray "DUPLICATE" label on the drawing. -Actioned, removed label Minor: * Revision…

  3. Hi Team, Against the request: * 1B: other frontage, truck reversing note (30 sec hold) and H&R are all shown. Good. * 7B: H&R and the second frontage are shown, but there's no note on the truck movements like on 1B, 2B and 5B. Truck route is only in the legend. Please add the same truck entry/exit note so it reads the same as the others. * S5 Daily Arrangement: Riri flagged S5. I can't see S5 referenced anywhere on the sheets. If the other frontage is running under the S5 daily TGS, add a "refer to CC05840-S5-xx" note so the TCs know which plan covers it. Needs fixing: * Options analysis sheets. The A sheets (2A, 5A and others) still say H&R isn't selected because holding traffic will conflict with the signals, but the B sheets now have the TC holding traffic and waiting for the signals to go red. Update the A sheets to match, and add a note on TC positioning relative to the signals. * Speed. Header says 40km/h but most of the ERW signs have 50 plates, with one 40. Confirm the posted limit on each approach (SP Blvd vs Markwell/Enderley) and make the ERW plates match. * 2B has a "Night works" label on the water meter removal. Is that meant to be there? If not, take it out. * 1B has a stray "DUPLICATE" label on the drawing. Minor: * Revision description just says "Updated TGS 1B, 2B, 5B, 7B, 8B, 10B". Spell out what changed (H&R, truck movements, concurrent frontage). The rev history rows are also showing twice on the cover. * Sheet design dates still show 12/08/2026. Only the…

  4. As discussed, please find attached the TGS suite for the civil works. Surfers Paradise Boulevard As mentioned, could you please let us know your requirements for the civil works on Surfers Paradise Boulevard? This could include the extent of the works, the proposed timing and staging, and any specific access requirements. Once we have this information, we can make sure the appropriate TGSs are prepared and the necessary permits are in place. TGS amendments in progress Neil is also working urgently on amendments to the TGSs. The updated designs will show: * The other frontage operating concurrently with the work zone * Truck entry and exit movements * Hold-and-release arrangements We will send the amended TGSs through as soon as they're finalised, so you have the complete suite to cover all stages of the works. If you have any questions about the attached TGSs, or anything you'd like included in the amendments, please let us know and we'll incorporate it. CC05840-TGS-S6-Rev01 1.pdf Plans folder: Plans CC05840 Suite: S6 - Civil_Service Connections Save work here: TGS > Rev 02 Project location: South Beach Project - Surfers Paradise Quote: none Job request form: none Request type: Amendment Scope: TGS

    • 9 Nov 2026, 4:23 pm · Riri D.

      TGS to amend 1B and 7B

    • 9 Nov 2026, 11:25 pm · Riri D.

      S5 - Daily Arrangement

  5. Hi Team! Please save work here: S5 - Daily Arrangement > Rev 02 Plans folder: Plans CC05840 Request: Please harmonize CC05840-S5-1C and CC05840-S5-6B as one plan and make it 7B. Tagging @K.G , @K.R @Neil Lancaster for any Q from planner. Thank you - Shaz

    • 28 Sep 2026, 2:23 pm · Neil Lancaster

      @B.R Please could you rephrase your question, surely all trucks would need priority?? ***************************************************************** B.R mentioned you in a reply on URGENT!! CC05840-S5 - Rev 2 - A Construct - South Beach - Surfers Paradise Blvd, Surfers Paradise ***************************************************************** Ongoing & Amendment Requests Allocated @K.R @K.G @Neil Lancaster Hello, could we please confirm which truck movements are to be given priority to include as a note on the plan. Thank you! 28 Sep 11:42 0 0 LikeReply on monday.com Reply to this email and it will magically appear in monday

    • 28 Sep 2026, 2:24 pm · B.R

      Hi @Neil Lancaster , Sorry kindy disregard my question. Thanks!

    • 28 Sep 2026, 3:15 pm · B.R

      Hi @Christopher Wright, This is uploaded and for review. Thank you! Folder Link: Plans CC05840 Files: TGS - CC05840-TGS-S5-Rev02.pdf TMP - CC05840-CTMP-Rev14.pdf Accounts: 1xTGS Add'l - CC05840-S5-7B Harmonisation Plan 1xTMP Amendment

    • 30 Sep 2026, 7:58 am · Christopher Wright

      This is GTG @Neil Lancaster

06Every file and folder

753 files in 198 folders. Type part of a name, a suite, a revision or a street to narrow the list. Sort by name or by date saved.

TypeNameFolderSaved