← All projectsCC06276
Project portal · built 17 Nov 2026, 10:03 am AEST · Review amendments

Myer Centre - Elizabeth Street

Hutchinson Builders

Harmonised works. This site's works affect a neighbouring site, so the traffic plans are harmonised. Each site stays its own job with its own CC. The other site is not named in the folder; check the harmonisation plans.

What's new

Monday updates and SharePoint changes, newest first

Full update log

Crompton Concepts prepares the traffic management for Hutchinson Builders on this project at 66 Elizabeth Street, Brisbane City QLD 4000, Australia. 2 Monday requests are open; the most pressing is at the review amendments stage; the current CTMP on SharePoint is Rev 05; 4 TGS suites on file (General no rev, S1 Rev 09, S2 Rev 03, S3 Rev 01). On the permit boards: 2 permits in force and 4 in progress. Monday holds 14 requests for this job (1 new, 13 amendments); all of them are on this page. Every file opens straight from SharePoint.

Client
Hutchinson Builders
Crompton job
CC06276
Location
66 Elizabeth Street, Brisbane City QLD 4000, Australia
LGA / authority
City of Brisbane
Project coordinator
C.C
Latest planner · TMD
Marie Est · Christopher Wright
Monday project status
New
Deliverables
TGS
Permits (Monday)
2 in force · 4 in progress
Last activity
16 Nov 2026
Files on SharePoint
319 in 92 folders

What needs attention now

  1. Review comments to action: CC06276-S1 - Rev 9 - Hutchinson Builders - Myer Centre - Elizabeth Street. Required by 14 Nov 2026 (overdue). Planner: Marie Est · TMD: Christopher Wright · Last note (16 Nov 2026, S.B): “Hi Marie, Nice work getting the aftercare sheets in. 14B (Initial Site Works – Site Inactive) and 15B/C/D (Crane/Barrier Alt Setup – Site Inactive) cover the 4B and 5B request,…”
  2. Complete, to be invoiced: CC06276-S1 - Rev 4 - Hutchinson Builders - Myer Centre - Elizabeth Street. Required by 11 Sep 2026. · Last note (10 Nov 2026, Sandy): “✓ IV0025823 - draft (1011)”
  3. Permit in progress: Footpath Closure: 24/7 Deposit Materials (Footpath) is Received/Holding. Follow up 10 Nov 2026. Wanted from 1 Dec 2026.
  4. Permit in progress: Internal Demolition and Fit Out (BCC road) is Initial Pending. Follow up 16 Nov 2026. Wanted from 11 Nov 2026.
  5. Permit in progress: DCP Testing (BCC road) is Council Pending. Follow up 26 Nov 2026. Wanted from 27 Nov 2026.
  6. Permit in progress: Road Daily Arrangement (BCC road) is Council Pending. Follow up 27 Nov 2026. Wanted from 1 Dec 2026.

PPermits

7 permit lines on the Monday permit boards: 2 in force, 4 in progress. Newest first within each state; closed and expired permits are at the bottom.

PermitAuthorityTypeStatusPeriodSentFollow upRenewalPermit no.
DCP Testing
Team Declan · BCC Road Permits - Declan
BCC roadDate SpecificIn progress
Council Pending
27 Nov 2026 – 27 Dec 20264 Nov 202626 Nov 2026
Road Daily Arrangement
Team Declan · BCC Road Permits - Declan
BCC roadOngoingIn progress
Council Pending
1 Dec 2026 – 30 Dec 202630 Oct 202627 Nov 202627 Nov 2026
Footpath Closure: 24/7 Deposit Materials
Team Declan · BCC Footpath Applications - Declan
FootpathOngoingIn progress
Received/Holding
1 Dec 2026 – 21 Feb 202719 Oct 202610 Nov 20264 Jan 2027
Internal Demolition and Fit Out
Team Declan · BCC Road Permits - Declan
BCC roadOngoingIn progress
Initial Pending
11 Nov 2026 – 2 Oct 20282 Nov 202616 Nov 2026
Full Road Closure: Line Marking Installation
Team Declan · BCC Road Permits - Declan
BCC roadDate SpecificIn force
Done
17 Nov 2026 – 30 Nov 202616 Nov 2026
Footpath: Propping
Team Declan · BCC Footpath Applications - Declan
FootpathDate SpecificIn force
Done
30 Sep 2026 – 30 Dec 20266 Oct 2026
OOH: Line Marking Installation
Team Declan · BCC Road Permits - Declan
BCC roadDate SpecificApproved, starts later
Done
19 Nov 2026 – 1 Dec 20263 Nov 2026

01New to the project? Start here

  1. 1

    Understand the job

    Start with the current traffic management plan, then the client's project information.

  2. 2

    Open the current TGS set

    Latest revision of each suite. Earlier revisions are in the register and the file list.

  3. 3

    Know the paperwork

    Project information, contacts, permits, quotes and invoices, as filed on SharePoint.

  4. 4

    Catch up on correspondence

    The latest emails saved into the project folder.

02Document register

Latest revision of each TMP, TGS suite and report, read from the revision folders and file names on SharePoint. Archived and superseded folders are left out.

03Requests on Monday

14 requests since 17 Apr 2026: 1 for new plans and 13 amendments to this job, newest first. Amendments stay on this page, never as a separate project.

RequestTypeSuiteRevStageRequestedRequired byPlannerTMD
CC06276-S1 - Rev 9 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS1Rev 09Review amendments
Internal Amendments
12 Nov 202614 Nov 2026Marie EstChristopher Wright
CC06276-S1 - Rev 8 - Hutchinson Builders - Myer Centre - Elizabeth Street UrgentAmendmentS1Rev 08Closed
No Charge
12 Oct 202614 Oct 2026
CC06276-S1 - Hutchinson Builders - Myer Centre - Elizabeth Street (TMP)Council RFIS1Closed
No Charge
28 Sep 202630 Sep 2026
CC06276-S1 - Rev 7 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS1Rev 07Closed
No Charge
28 Sep 202630 Sep 2026
CC06276-S1 - Rev 5 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS1Rev 05Closed
No Charge
23 Sep 202625 Sep 2026
CC06276-S1 - Rev 6 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS1Rev 06Closed
No Charge
23 Sep 202625 Sep 2026
CC06276-S2 - Rev 3 - Hutchinson Builders - Myer Centre - Elizabeth StreetCouncil RFIS2Rev 03Invoiced
Invoiced
17 Sep 202619 Sep 2026
CC06276-S1 - Rev 4 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS1Rev 04To invoice
Invoice Scheduled
9 Sep 202611 Sep 2026
CC06276-S1 - Rev 3 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS1Rev 03Invoiced
Invoiced
12 Aug 202619 Aug 2026
CC06276- S3 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS3Invoiced
Invoiced
30 Jul 20261 Aug 2026
CC06276-S1 - Rev 1 & 2 - Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS1Rev 01Invoiced
Invoiced
9 Jul 202613 Jul 2026
CC06276-S2 - Rev 1 & 2- Hutchinson Builders - Myer Centre - Elizabeth StreetAmendmentS2Rev 01Invoiced
Invoiced
23 Jun 202625 Jun 2026
CC06276 - S2 - Hutchinson Builders - Myer Centre - Elizabeth StreetCouncil RFIS2Invoiced
Invoiced
10 Jun 202612 Jun 2026
CC06276 - Hutchinson Builders - Myer Centre - Elizabeth StreetNew plansInvoiced
Invoiced
17 Apr 202621 Apr 2026

04Who's who

From the Contact folders on SharePoint and the people assigned on Monday. Check the project information folder for the latest contact list.

Client / site

  • !! Archived
  • ACCOUNTS

Crompton Concepts

  • Marie EstPlanner
  • Christopher WrightTMD
  • C.CProject coordinator (Monday)

05Update log

Monday updates and replies on this project's requests, newest first.

  1. Hi Marie, Nice work getting the aftercare sheets in. 14B (Initial Site Works – Site Inactive) and 15B/C/D (Crane/Barrier Alt Setup – Site Inactive) cover the 4B and 5B request, the "NO LINES" sign the client asked for is on both, and the CTMP Rev 5 change log and figure list (Figs 17 and 21) pick them up. 1. Site-active items left on the aftercare sheets (15B/15C/15D) * 15B still shows "270 m Estimated Queue (5 mins Hold while lifting over the lane)", and 15B, 15C and 15D all carry PREPARE TO STOP / QUEUED TRAFFIC AHEAD signs. There's no hold or lift after hours, so these signs would be warning drivers about a queue that doesn't exist. Please remove the queue callout and the PREPARE TO STOP / QUEUED TRAFFIC AHEAD signs (or show them covered) on all three sheets. Leave only what stays overnight: the lane closure, tapers, ROADWORK AHEAD / DO NOT OVERTAKE, NO LINES and END ROADWORK. * If 15C/15D only existed to carry the advance queue warning on George St / William St, check whether they're still needed at all once those signs are gone. 2. JOINS labels * 15B says "Joins 3D / Joins 3C / Joins 3E", which was copied from 3B. They should point to 15C and 15D. * 15C and 15D both say "Joins 5B". They should say "Joins 15B" (the CTMP figure titles already say "joins 15B"). 3. 14A / 15A options sheets * 14A "Minimum TGS Assets" shows TC (Including Breaks): 1 and TC Vehicle: 1. For a site-inactive sheet these should be 0. Please check 15A too. * 14A reasoning says the "combined traffic…

  2. Plans sent to client by Dec - Shaz 121126 Dec moved to No charge Re_ Update Uptown TGS.eml

  3. Clients Request: "Could you please add an Aftercare TGS to S1-4B, and S1-5B. We need signage that says “New Work No Lines” or similar as there will be days between line marking with stick and stomps / temporary markings" Plans folder: Plans - CC06276 Suite: S1 Save work here: TGS > Rev 09 TMP > Rev 05 Project location: Myer Centre - Elizabeth Street Quote: none Job request form: none Request type: Amendment Scope: TGS & TMP Fw_ Update Uptown TGS.eml

    • 13 Nov 2026, 8:02 am · Marie Est

      Hello @Christopher Wright , The TGS S1 has already been amended and uploaded to the folder. Please review it at your convenience. * 1x New TGS on S1 - CC06276-S1-14B - Initial Site Works - Site Inactive * 1x New TGS on S1 - CC06276-S1-15B - Crane Install/Mobile Crane/Barrier install (Alternative Setup) - Site Inactive * 1x TMP Amendment - CC06276-S1-TMP-Rev 5 - Additional figures for additional TGS. Link: TGS - Rev 9 TMP - Rev 5

  4. ✓ IV0025823 - draft (1011)

  5. Charge 4 x TGS in response to client email Uptown - TGS for Bus Stop Works.eml

  6. leave for now as per Riri Still waiting for Rihanna's confirmation if charges are correct

  7. IV0025599 - draft (2010) 1x new TGS

  8. 1 x New TGS - Harmonisation Plan

  9. Specific operations: Do additional TGS's for bus stops as per markup from client saved in Rev 4. Also do 2 X Additional TGS's for DCPs testing, this will only be place for 2 hours in each closure. TGS to amend: 2x

  10. No charge - per Chelsea

  11. Chelsea advised no charge - wrong amendment

  12. Also amend the TMP please

  13. Hi @Y.B Please save work here: Rev 08 S1: S1 Mark-up: CC06276-S1-6B can this TGS please be updated. Please see attached mark up that has been largely agreed with QSM in relation to Albert St. We will set the concrete barriers hard up to the trees. Can you please update the TGS to show 2 x TC, as well as get a site plan from Dare. Could you please target Wednesday 14th for the TGS. A&E Corner Early Works Barriers - rev 1.pdf Site Mark Up 1.pdf Fw_ Additional TGS - Albert _ Elizabeth .eml Thanks - Shaz

    • 12 Oct 2026, 12:59 pm · Y.B

      Hi @Christopher Wright, I've amended the TGS and updated the CTMP. Files have been uploaded to Sharepoint for your review. Please let me know if any changes are required. Thank you! 1x TGS Amendment (CC06276-S1-6B) -Amended TGS 6B to add concrete barrier with gawk screen, fencing panel, and additional TC; pedestrian management updated Rev 08: Sharepoint - Documents - Rev 08 - All Documents 1x TMP Amendment -Updated section 8.5.1 Rev 04: Sharepoint - Documents - Rev 04 - All Documents

    • 14 Oct 2026, 11:56 am · Christopher Wright

      This is GTG

  14. @D.B 1xTGS added for emergency propping works. TGS 13 and TMP section 8.8 for reference TMP: Rev 03 TGS: Rev 07

  15. Hi Plans folder: Plans - CC06276 Suite: S1 Save work here: TGS > Rev 07 TMP > Rev 03 Project location: Myer Centre - Elizabeth Street Email Attached: Fw_ Uptown - Elizabeth & Albert Street Propping.eml Thank you! 🧡Kim

    • 29 Sep 2026, 1:34 pm · Christopher Wright

      This is GTG

  16. Hi @Y.B Please save work here: TMP > Rev 03 Plans folder: Plans - CC06276 Instructions: As discussed in todays meeting with council, could you please add the following to the CTMP as appendices * RPEQ Layout Elizabeth St * RPEW Cycle Survey/Layout and advice Could you please have this updated on Monday. RPEQ Cycle Advice.pdf 26-079 CYCLE DEMAND - Survey 24th - 26th June [v01a]..pdf 26-079.100SET Rev.A CERT.pdf RE_ Uptown Traffic Management Review.eml Thanks - Shaz

    • 28 Sep 2026, 5:01 pm · Y.B

      @D.B Hi @Christopher Wright, I've amended the CTMP. Please let me know if changes are required. Thanks! 1x CTMP Amendment -Council Request: Additional Appendices for RPEQ Layout Elizabeth St and RPEW -Cycle Survey/Layout and advice -Updated Figures: TGS 3 and 5 -Additional Sections for Bus Stop Works and DCP Testing Sharepoint - Documents - Rev 03 - All Documents

    • 29 Sep 2026, 1:11 pm · Christopher Wright

      This is GTG

  17. @C.C you commented on S2 this plan is supposedly for TMD review. your request is for S1 rev 5 amendment. Adding it here separately to avoid confusion. @Y.B fyi Plans folder: Plans - CC06276 Suite: S1 Save work here: TGS > Rev 05 TMP > n/a Project location: Myer Centre - Elizabeth Street

    • 23 Sep 2026, 1:01 pm · Riri D.

      @Christopher Wright adding your comment here as this is supposedly for the S1 Rev 5 amendment not their S2 amendment. Hi @Y.B it appears that a roadwork ahead is missing If the traffic lights are being turned off the the traffic light insert will need to replace the workman insert, the taper length is missing and a roadwork ahead is also missing. Please use yellow blanks or speed signs when motorists cannot see workers, the workman symbolic are too far away to be used. This lane stat is not required.

    • 23 Sep 2026, 1:11 pm · Y.B

      Hi @C.C @Christopher Wright, just wanted to clarify if we still need to make changes with the signage (see below) as these are for Lindores Personnel. Also, taper length weren't provided in the TGS reference. Could you please confirm if we still need to reflect those? Thank you!

    • 23 Sep 2026, 1:17 pm · Christopher Wright

      As it appears that Cromptons did not design the Lindores TGS don't worry about it. If any changes i have requested are from what we designed, then please change it.

    • 23 Sep 2026, 2:17 pm · Y.B

      Hi @Christopher Wright, all revisions in Rev 5 have been applied in the most recent verion (Rev 6). Please refer to Rev 6. Thank you! Monday Link: (4) Ongoing & Amendment Requests - CC06276-S1 - Rev 6 - Hutchinson Builders - Myer Centre - Elizabeth Street SHarePoint Link Rev 6: Sharepoint - Documents - Rev 06 - All Documents

    • 24 Sep 2026, 8:09 am · Christopher Wright

      This is GTG

  18. @C.C this is for the minor amendment you requested. We separate it so @Y.B won't be confused. Plans folder: Plans - CC06276 Suite: S1 Save work here: TGS > Rev 06 TMP > n/a Project location: Myer Centre - Elizabeth Street RE_ Uptown - TGS for Bus Stop Works.eml

    • 23 Sep 2026, 2:14 pm · Y.B

      @C.C Hi @Christopher Wright, I've amended TGS CC06276-S1-8B to maintain pedestrian access to Uptown and use the nearest bus stop, as requested by the client. I've also updated TGS CC06276-S1-3B and CC06276-S1-5B based on your comments in Rev 5 (See comment link: https://cromptonconcepts.monday.com/boards/9116084711/pulses/13111230437/posts/5570666861?reply=repl...) Please let me know if any changes are required. Thank you! 1x TGS Amendment TGS CC06276-S1-8B TGS Rev 06: Sharepoint - Documents - Rev 06 - All Documents

    • 24 Sep 2026, 8:27 am · Christopher Wright

      This is GTG

  19. Hi @Y.B Plans folder: Plans - CC06276 Suite: S2 - Harmonisation Plan Save work here: TGS > Rev 03 Project location: Myer Centre - Elizabeth Street Quote: Request type: Amendment Scope: TGS Specific operations: harmonize a plan between the TGS that Gina sent through and our Road Closure TGS. So to have both closures on one TGS. TGS to amend: 1x Client mark-ups/attachments: Any specific files the planner needs to refer to? LP 1997-2 Additinal Signs Ahead.pdf LP 1997 r003 - Full Road Closure Eagle St.pdf Attention Chelsea RC-15048.eml

    • 18 Sep 2026, 1:00 pm · Y.B

      @Sandy @C.C Hi @A.A, I've harmonised the attached plans to TGS CC06276-S2-1A and CC06276-S2-2A. Please let me know if changes are needed. Thank you! 2x TGS Amendment CC06276-S2-1A/1B - Deliveries CC06276-S2-2A/2B - Demolition Sharepoint - Documents - Rev 03 - All Documents

    • 21 Sep 2026, 1:09 pm · C.C

      @Y.B Amend as per teams chat

    • 21 Sep 2026, 5:41 pm · Y.B

      @C.C Hi @A.A, I've hamonized TGS (CC06276-S1-3B) with TGS (LP 1997 r003). Please let me know if there's any changes needed. Thanks! PLEASE NOTE: This amendment is for S1 - Revision 05 1x Amendment (CC06276-S1-3B) Sharepoint - Rev 05 - All Documents

    • 22 Sep 2026, 1:38 pm · Christopher Wright

      Hi @Y.B it appears that a roadwork ahead is missing If the traffic lights are being turned off the the traffic light insert will need to replace the workman insert, the taper length is missing and a roadwork ahead is also missing. Please use yellow blanks or speed signs when motorists cannot see workers, the workman symbolic are too far away to be used. This lane stat is not required.

    • 22 Sep 2026, 2:00 pm · Y.B

      Hi @Christopher Wright, just wanted to clarify if we still need to make changes with the signage (see below) as these are for Lindores Personnel. Also, taper length weren't provided in the TGS reference. Could you please confirm if we still need to reflect those? Thank you!

    • 23 Sep 2026, 1:03 pm · Riri D.

      @Christopher Wright this is for TMD review. The above amendment is for S1 rev 5 allocation please check https://cromptonconcepts.monday.com/boards/9116084711/pulses/13111230437

    • 23 Sep 2026, 1:37 pm · Christopher Wright

      This is GTG

  20. Posted by Ykath (ykath@cromptonconcepts.com.au) · @Y.B via Work Flow RapidPlan screenshot skipped: No plan file for this task Links * TGS - S1- Rev 04

  21. Chelsea team catch up 10-09-26.pdf Invoice along with S1-Rev 1 & 2 1x TGS new CC06276-S1-6B - Albert St - Small Deliveries

    • 11 Sep 2026, 2:21 pm · Permits

      IV0025242- Draft

    • 16 Sep 2026, 10:40 am · Permits

      IV0025248 - please use this. Thanks! 1 TGS NEW

  22. Chelsea team catch up 10-09-26.pdf Invoice along with S1-Rev 3 2x TGS new (3B & 4B) 2x TGS amended (major revisions for 1B & 2B) 1x Full CTMP 3290 1x RA

    • 11 Sep 2026, 2:20 pm · Permits

      IV0025242- Draft

  23. Hi @Y.B Plans folder: Plans - CC06276 Suite: S1 Save work here: TGS > Rev 04 Project location: Myer Centre - Elizabeth Street Quote: N/A Request type: Additional Scope: TGS Specific operations: Do additional TGS's for bus stops as per markup from client saved in Rev 4. Also do 2 X Additional TGS's for DCPs testing, this will only be place for 2 hours in each closure. TGS to amend: 2x Client mark-ups/attachments: Bus Stop Relocation TGS Mark Up.pdf ECC-HB-542HC-L-LIFTPLAN-RevA- DCP works on Elizabeth.pdf Uptown-Short notice permit request.eml Uptown - TGS for Bus Stop Works.eml

    • 14 Sep 2026, 12:35 pm · Y.B

      @C.C Hi @A.A I've uploaded in Sharepoint the additional TGSs for your review. Please let me know if any changes are required. Thank you! 6x Additional TGS CC06276-S1-7B - Elizabeth St - Bus Stop Works (Stop 83) CC06276-S1-8B - Elizabeth St - Bus Stop Works (Stop 82) CC06276-S1-9B - Elizabeth St - Bus Stop Works (Stop 81) CC06276-S1-10B - Elizabeth St - Bus Stop Works (Stop 97) CC06276-S1-11B - Elizabeth St - Elizabeth St - DCP 1 Testing CC06276-S1-12B - Elizabeth St - Elizabeth St - DCP 2 Testing Sharepoint - Documents - Rev 04 - All Documents

    • 18 Sep 2026, 1:34 pm · Christopher Wright

      This is GTG @C.C

    • 21 Sep 2026, 6:28 pm · C.C

      Hi @Y.B the site has asked for some minor amendments I have added this in the new folder. TGS

    • 22 Sep 2026, 10:22 am · Y.B

      Hi @C.C, I checked the Sharepoint folder but couldn't find any email or attachments regarding the amendment. Could you kindly reupload them? Thank you!

    • 22 Sep 2026, 12:26 pm · Y.B

      Hi @C.C @Riri D., could I please follow up on the amendment details? Thank you!

    • 23 Sep 2026, 12:43 pm · Riri D.

      @Y.B Rev 06

  24. Plans sent to client - Additional TGS - Albert _ Elizabeth .eml

  25. Amended plans sent to client - Re_ Uptown Traffic Management Review.eml

06Every file and folder

319 files in 92 folders. Type part of a name, a suite, a revision or a street to narrow the list. Sort by name or by date saved.

TypeNameFolderSaved