60 Queen St
Built
Other Crompton jobs at this address, for a different client: Demex (CC06519), INZ Electrical (CC06533). They are separate jobs with their own CC numbers.
What's new
- 6 Nov 20269 files saved on SharePoint: CC06117-S1-CTMP-Rev0.pdf, CC06117-S1-TMP-Rev0.pdf, CC06117-S1-TMP-Rev0.docx, CC06117-S1-TIA-Rev0.pdf and 5 more
- 3 Nov 2026, 5:46 pmRiri D. on CC06117-S1 - TMP - Built - 60 Queen St: Plans folder: Plans - CC06117 Suite: S1 Save work here: NEW TMP > Rev 00 Project location: 60 Queen St Quote: none Job request form: none No TGS amendments but Create a TMP, Risk and queue length, please use DEMEX TMP for help if needed (Same location,…
- 20 Oct 2026, 11:35 amPermits on CC06117-S1 - Rev 2 - Built - 60 Queen St: IV0025625 sent to client - Shaz 2010 2x 5tgs Invoice IV0025625 from Crompton Concepts for Built - 60 Queen St.eml
- 20 Oct 2026, 11:30 amPermits on CC06117-S1 - Built - 60 Queen St: IV0025625 sent to client - Shaz 2010 1x 5tgs Invoice IV0025625 from Crompton Concepts for Built - 60 Queen St.eml
- 19 Oct 2026, 10:15 amK.R on CC06117-S1 - Rev 4 - Built - 60 Queen St: No charge - minor Amendment
- 19 Oct 2026, 10:10 amK.R on CC06117-S1 - Rev 2 - Built - 60 Queen St: 2x Additional TGS CC06117-S1-3A/3B - Tower Crane Installation/Dismantle - Full Road Closure (George St) with Hold and Release (QPS assistance-Elizabeth St) CC06117-S1-4A/4B - Service Connections - Full Road Closure (Burnett Ln)
Crompton Concepts prepares the traffic management for Built on this project at George St & Elizabeth St, Brisbane City QLD 4000, Australia. No Monday request is open right now; the latest one closed recently; the current CTMP on SharePoint is Rev 00; 2 TGS suites on file (General Rev 03, S1 Rev 06). Monday holds 6 requests for this job (2 new, 4 amendments); all of them are on this page. Every file opens straight from SharePoint.
- Client
- Built
- Crompton job
- CC06117
- Location
- George St & Elizabeth St, Brisbane City QLD 4000, Australia
- LGA / authority
- City of Gold Coast
- Project coordinator
- C.C
- Latest planner · TMD
- —
- Monday project status
- New
- Deliverables
- TGS
- Permits (Monday)
- None on the permit boards
- Last activity
- 6 Nov 2026
- Files on SharePoint
- 68 in 64 folders
What needs attention now
- Nothing open on Monday. The latest request is closed or invoiced; this project stays on the list while it had activity in the last 120 days.
PPermits
Permits are tracked on the Monday team permit boards and the Permit Register.
No permits for this job on the Monday permit boards. If permits are needed, they have not been set up there yet.
01New to the project? Start here
- 1
Understand the job
Start with the current traffic management plan, then the client's project information.
- PDFCC06117-S1-CTMP-Rev0.pdfCTMP Rev 00 · 6 Nov 2026
- PDFBuilt Minor Consultancy Agreement Executed.pdf28 Apr 2026
- 2
Open the current TGS set
Latest revision of each suite. Earlier revisions are in the register and the file list.
- 3
Know the paperwork
Project information, contacts, permits, quotes and invoices, as filed on SharePoint.
- 4
Catch up on correspondence
The latest emails saved into the project folder.
- EML60 Queen Street_Invoices To2 Nov 2026
- EMLRE JL - 4368 - Barrier Fence Review - Tribune St7 Sep 2026
- EMLFW George St Mobile Crane setup7 Sep 2026
- EMLRE Built - 60 Queen St Fee Proposal 22 Jul 2026
- EMLRE Built 60 Queen St Burnett Lane Swept Path Assistance 22 Jul 2026
02Document register
Latest revision of each TMP, TGS suite and report, read from the revision folders and file names on SharePoint. Archived and superseded folders are left out.
| Suite | Document | Latest | Saved | Revs | Current files |
|---|---|---|---|---|---|
| — | CTMP | Rev 00 | 6 Nov 2026 | 1 | CC06117-S1-CTMP-Rev0.pdf |
| — | TMP | Rev 00 | 6 Nov 2026 | 1 | 26-052.01-1a NTB Layout (Detail) v2.pdfCC06117-S1-TMP-Rev0.pdf |
| — | RA | Rev 00 | 6 Nov 2026 | 1 | CC06117-S1-RA-Rev0.pdf |
| — | TIA | Rev 00 | 6 Nov 2026 | 1 | CC06117-S1-TIA-Rev0.pdf |
| General | TGS | Rev 03 | 7 Sep 2026 | 2 | 250325-DRG-LA-BUQS-1.2 Erection & Dismantle Requirements.pdfExisting services.pdf |
| S1 | TGS | Rev 06 | 28 Sep 2026 | 7 | CC06117-S1-R6.pdf |
03Requests on Monday
6 requests since 19 Jan 2026: 2 for new plans and 4 amendments to this job, newest first. Amendments stay on this page, never as a separate project.
| Request | Type | Suite | Rev | Stage | Requested | Required by | Planner | TMD |
|---|---|---|---|---|---|---|---|---|
| CC06117-S1 - TMP - Built - 60 Queen St | Amendment | S1 | Closed No Charge | 3 Nov 2026 | 5 Nov 2026 | |||
| CC06117-S1 - Rev 5 - Built - 60 Queen St Urgent | Amendment | S1 | Rev 05 | Closed No Charge | 25 Sep 2026 | 27 Sep 2026 | ||
| CC06117-S1 - Rev 4 - Built - 60 Queen St | Amendment | S1 | Rev 04 | Closed No Charge | 24 Sep 2026 | 26 Sep 2026 | ||
| CC06117-S1 - Rev 2 - Built - 60 Queen St | Amendment | S1 | Rev 02 | Invoiced Invoiced | 2 Sep 2026 | 4 Sep 2026 | ||
| CC06117-S1 - Built - 60 Queen St | New plans | S1 | Invoiced Invoiced | 20 May 2026 | 22 May 2026 | |||
| CC06117 - Built - 60 Queen St | New plans | Closed No charge | 19 Jan 2026 | 1 Jan 1970 |
04Who's who
From the Contact folders on SharePoint and the people assigned on Monday. Check the project information folder for the latest contact list.
Client / site
- !! Archived
- ACCOUNTS
- ACCTSinvoices@built.com.au
- CCjonathanmoore@built.com.au
- SM Jake Farley0466 326 701
- SM Email Address
- SM Phone Number
- WHS Name - Email
- WHS Name - Phone Number
- WHS Email Address
- WHS Phone Number
Crompton Concepts
- C.CProject coordinator (Monday)
05Update log
Monday updates and replies on this project's requests, newest first.
- 3 Nov 2026, 5:46 pm · Riri D. · CC06117-S1 - TMP - Built - 60 Queen St
Plans folder: Plans - CC06117 Suite: S1 Save work here: NEW TMP > Rev 00 Project location: 60 Queen St Quote: none Job request form: none No TGS amendments but Create a TMP, Risk and queue length, please use DEMEX TMP for help if needed (Same location, different layout) DEMEX TMP > Rev 07
- 4 Nov 2026, 3:28 pm · J.R
Hi @Riri D. what TGS should i base the new TMP?
- 4 Nov 2026, 4:35 pm · Riri D.
@J.R Construction Plans
- 6 Nov 2026, 9:57 am · J.R
Hi @Christopher Wright @D.B TMP, TIA and DRA are now available for review. Thank you! Please note that the TGS aren't revised/ amended. TMP: Rev 00 Accounts: 1x Full CTMP 1x Full TIA 1x DRA
- 4 Nov 2026, 3:28 pm · J.R
- 20 Oct 2026, 11:35 am · Permits · CC06117-S1 - Rev 2 - Built - 60 Queen St
IV0025625 sent to client - Shaz 2010 2x 5tgs Invoice IV0025625 from Crompton Concepts for Built - 60 Queen St.eml
- 20 Oct 2026, 11:30 am · Permits · CC06117-S1 - Built - 60 Queen St
IV0025625 sent to client - Shaz 2010 1x 5tgs Invoice IV0025625 from Crompton Concepts for Built - 60 Queen St.eml
- 19 Oct 2026, 10:15 am · K.R · CC06117-S1 - Rev 4 - Built - 60 Queen St
No charge - minor Amendment
- 19 Oct 2026, 10:10 am · K.R · CC06117-S1 - Rev 2 - Built - 60 Queen St
2x Additional TGS CC06117-S1-3A/3B - Tower Crane Installation/Dismantle - Full Road Closure (George St) with Hold and Release (QPS assistance-Elizabeth St) CC06117-S1-4A/4B - Service Connections - Full Road Closure (Burnett Ln)
- 19 Oct 2026, 10:02 am · K.R · CC06117-S1 - Built - 60 Queen St
2 x TGS - Chargeable
- 25 Sep 2026, 12:44 pm · Permits · CC06117-S1 - Rev 5 - Built - 60 Queen St
Hi team! Please save work here: Rev 05 Plans folder: Plans - CC06117 Mark-up by client: 2026-09-25 - CC6117-S1-R2 - Annexure AH DRAFT MARKUP.pdf Fw_ 60QS - Updated TGS.eml @D.B will add more details thanks - Shaz
- 25 Sep 2026, 12:55 pm · D.B
@Y.B let me know when you are free and we'll have a quick meeting in regards to this
- 25 Sep 2026, 2:58 pm · Y.B
@D.B Hi @Christopher Wright, I've revised the TGS and uploaded it in SharePoint for your review. Please let me know if revisions are required. Thank you! 4x TGS Amendment (TGS 1B - 4B) Client Request: - Specified Legend items as "By others" across all TGSs - Added full road closure in Burnett Ln in TGS (3B) - Extended and added Hoarding details - Added insert for truck movement from Burnett Ln - Removed pedestrian fence opposite the worksite - Extended construction site to the footpath - Reflected the work zone in the parking lane Rev 05: Sharepoint - Documents - Rev 05 - All Documents
- 25 Sep 2026, 3:20 pm · D.B
@Y.B thank you, 2 things. Show by others only on the legend please Show cops on this
- 25 Sep 2026, 3:41 pm · Y.B
Hi @D.B @Christopher Wright plans have been updated. Thanks!
- 28 Sep 2026, 12:52 pm · D.B
@Y.B , Please see below clients comments, can this TGS please be amended rev ing up please. 2026.09.28 - CC06117-S1-R5 - Built Comments.pdf
- 28 Sep 2026, 1:41 pm · Y.B
@D.B Hi @Christopher Wright, I've revised the TGSs and uploaded them in Sharepoint for your review. Thanks! 2x TGS Amendment CC06117-S1-1B - Notes revised/rephrased as per client request CC06117-S1-2B - Notes revised/rephrased as per client request Rev 06: Sharepoint - Documents - Rev 06 - All Documents
- 25 Sep 2026, 12:55 pm · D.B
- 24 Sep 2026, 9:21 am · Sandy · CC06117-S1 - Rev 4 - Built - 60 Queen St
Hi @Y.B Plans folder: Plans - CC06117 Suite: Construction Plans Save work here: TGS > Rev 04 Project location: 60 Queen St Quote: N/A Request type: Amendment Scope: TGS Specific operations: Please remove the wording Gantry on Queen St frontage and put 6m wide hoarding on all TGS's. TGS to amend: Client mark-ups/attachments: Any specific files the planner needs to refer to?
- 24 Sep 2026, 10:51 am · Y.B
Hi @A.A, I've revised the TGS and uploaded it in SharePoint for your review. Please let me know if any changes are needed. Thank you! 4x TGS Amendment (TGS 1B -4B) -Removed Gantry and note in TGS 1B and 2B -Added Hoarding in all TGSs Sharepoint - Documents - Rev 04 - All Documents
- 24 Sep 2026, 11:19 am · Christopher Wright
This is GTG @C.C
- 24 Sep 2026, 10:51 am · Y.B
- 7 Sep 2026, 1:51 pm · C.C · CC06117-S1 - Rev 2 - Built - 60 Queen St
@Y.B Please design the tower crane installation TGS as per below - I have saved the crane study in rev 3, please overlay this on the TGS. See extra details from the client - Brief summary is as follows: * Crane climbs down to the first tie in on Level 10. Franna working in loading zone to load out towers. * Mobilise 350t to George st – Trucks will need to reverse into George st from Elizabeth st for this * Remove outer section of jib over the mall noting the exclusion zone we will require. – again trucks will need to reverse into George st to take the jib away. * Dismantle remainder of TC facing towards Adelaide st including any grillage components located externally on the building – trucks to reverse into George st from Adelaide st end. * Demob mobile crane – trucks again from Elizabeth It would be a really rough guess on the duration but it would be something like the following: * Climb Down – 2-3 days * Mobile crane mob – 2-3hrs * Outer jib removal – 1-2hrs * Balance of crane dismantle – 12-14hrs * Mobile crane demob – 2-3 hrs
- 7 Sep 2026, 1:51 pm · C.C
@Y.B Construction Plans
- 7 Sep 2026, 3:38 pm · C.C
@Y.B @A.A further plans to be completed - * Add in CTMP that New Energex pit connection is on George St footpath - can be done within the daily arrangement.( please add the details in CTMP for staging purposes) * Add in CTMP that the below can be done under daily for staging 1 x New UU Water Connections 2 x existing on George St Footpath our side of the road 1 x New on George St Footpath crossing George St to our site - If done after demo and site setup, can be done within the daily arrangement. * 1 x New Stormwater Connection on Burnett Lane - Burnett lane full closure * New Sewer Connection on Burnett Lane, cap and seal of redundant connections on Burnett Lane - Burnett lane full closure Have saved email and attachments in the folder
- 8 Sep 2026, 9:30 am · Y.B
Hi @C.C @A.A, additional TGSs have been uploaded for review. Please let me know if any changes are needed. Thank you! Also @C.C, regarding CTMP, do we have an existing CTMP, or do we need a new one? -If there's an existing CTMP, could I please have a copy of the word file or the sharepoint link? I checked the Construction Plans folder and could not find the CTMP. -If we need a new CTMP, just wanted to confirm if it's going to be a full TMP? Could I also request a copy of the Project Information form? Thank you! 2x Additional TGS CC06117-S1-3A/3B - Tower Crane Installation/Dismantle - Full Road Closure (George St) with Hold and Release (QPS assistance-Elizabeth St) CC06117-S1-4A/4B - Service Connections - Full Road Closure (Burnett Ln) Sharepoint - Documents - Rev 03 - All Documents
- 10 Sep 2026, 12:56 pm · Y.B
@C.C @Riri D. Hi @A.A, I've added 2x additional TGS and have uploaded the plans in SharePoint for your review. Please let me know if we need to make any changes with the plans. Thank you. Also, CTMP is to follow. We're still waiting for approval. 2x Additional TGS CC06117-S1-3A/3B - Tower Crane Installation/Dismantle - Full Road Closure (George St) with Hold and Release (QPS assistance-Elizabeth St) CC06117-S1-4A/4B - Service Connections - Full Road Closure (Burnett Ln) Sharepoint - Documents - Rev 03 - All Documents
- 22 Sep 2026, 11:32 am · Christopher Wright
Hi @Y.B Please use "Road Closed Ahead" with directional arrow when the road closure is not implemented at the intersection. I have amended this so no further action required. This is GTG @C.C
- 7 Sep 2026, 1:51 pm · C.C
- 2 Sep 2026, 6:06 pm · Riri D. · CC06117-S1 - Rev 2 - Built - 60 Queen St
Plans folder: Plans - CC06117 Suite: Prelodgement TGS Save work here: TGS > TMP > Project location: 60 Queen St Quote: none Request type: Amendment Scope: TGS Specific operations: TGS to amend: Client mark-ups/attachments: 2026.09.01 - Burnett Lane Gantry Clash - Combined Markup inc Hoarding for OCS.pdf RE_ 60 Queen Street - Burnett Lane Gantry .eml
- 2 Sep 2026, 6:06 pm · Riri D.
PENDING DETAILS
- 3 Sep 2026, 11:24 am · Y.B
Hi @C.C @Riri D. , just wanted to ask for clarifications and additional details. 1. I checked the Rev 1 version of CC06117 - S1 - Built - 60 Queen Street, currently we don't have a TGS specific for the gantry works on Burnett Lane. To clarify, do we need an additional TGS for this specific work? If yes, could you please provide the specific details of the work (operation, number of TC's needed, etc) 2. Could I please request for a copy of the updated swept path? Thank you.
- 4 Sep 2026, 9:44 am · Riri D.
@Y.B here is the SP for their RPEQ (Swept Path) - RPEQ. As for the gantry works I will check with Chelsea Will tagged this as request info
- 4 Sep 2026, 10:50 am · C.C
@Y.B amend the current TGS, not an additional TGS. Don't worry about the swept path as that is still in discussion. This is preliminary.
- 4 Sep 2026, 11:59 am · Y.B
@Riri D. Hi @C.C, requesting more details on the amendment. The email contains only the discussion about moving specific columns to allow safe truck manoeuvre. (See image below) Currently, we don't have any closures on Burnett Lane in 2 TGSs. Could you please specify which TGS will have amendments? (See image below)
- 4 Sep 2026, 12:32 pm · Y.B
Hi @A.A, as instructed by @C.C, I added Gantry on Burnett Lane. TGS has been uploaded for your review. Thanks! 2x TGS Amendment CC06117-S1-1B - Added Gantry on Burnett Lane CC06117-S1-2B - Added Gantry on Burnett Lane Sharepoint - Documents - Rev 02 - All Documents